On January 6, Liana and I emptied and dried the fish tank, washed it with warm water, and dried it again. We polished light guides. It took me much longer than it took her. I might have been pressing too hard. I measured the length and width of 30 scintillating fibers. I counted scintillating fibers and put them in relabeled bags. | On January 6, Liana and I emptied and dried the fish tank, washed it with warm water, and dried it again. We polished light guides. It took me much longer than it took her. I might have been pressing too hard. I measured the length and width of 30 scintillating fibers. I counted scintillating fibers and put them in relabeled bags. | ||
− | On January 7, I learned how to screw the collars onto the Unistrut bar. I scraped rust off the bar with a damp cloth. Kenny and I made two bundles of fibers for Brendan to mill. The collars have to be 65 10/16" apart on the outside. | + | On January 7, I learned how to screw the collars onto the Unistrut bar. I scraped rust off the bar with a damp cloth. Kenny and I made two bundles of fibers for Brendan to mill. The collars have to be 65 10/16" apart on the outside. I polished a bundle of light guides and then polished some individual fibers that had not been polished enough in the bundle. |
+ | |||
+ | On January 8, I went to the machine shop with Jon to pick up a milled bundle. I put a bundle on the Unistrut bar to be straightened, and I cleaned some fibers that Jon had polished. |
Revision as of 16:31, 8 January 2014
On January 2, I helped straighten a bundle after cleaning a bundle that had already been straightened. Then I revised an old version of the straightening procedure and typed two other procedures.
On January 6, Liana and I emptied and dried the fish tank, washed it with warm water, and dried it again. We polished light guides. It took me much longer than it took her. I might have been pressing too hard. I measured the length and width of 30 scintillating fibers. I counted scintillating fibers and put them in relabeled bags.
On January 7, I learned how to screw the collars onto the Unistrut bar. I scraped rust off the bar with a damp cloth. Kenny and I made two bundles of fibers for Brendan to mill. The collars have to be 65 10/16" apart on the outside. I polished a bundle of light guides and then polished some individual fibers that had not been polished enough in the bundle.
On January 8, I went to the machine shop with Jon to pick up a milled bundle. I put a bundle on the Unistrut bar to be straightened, and I cleaned some fibers that Jon had polished.